Carmichael Coal Mine and Rail Project

Project overview*

EIS status EIS active
Description Open-cut and underground coal mine with a yield of 60 million tonnes per annum (from 2022); and railway line.
Proponent Adani Mining Pty Ltd, a wholly owned subsidiary of India's Adani Group.
Location/s
  • Mine: Galilee Basin, 160 km north-west of Clermont
  • Railway line: from the mine to Moranbah, where it will join the existing Goonyella rail system.
Map
Local government/s
  • Isaac Regional Council (majority of mine and rail)
  • Charters Towers Regional Council (small portion of mine)
Key features
  • open-cut and underground coal mine
  • approximately 190-kilometre railway line
  • off-site infrastructure, including accommodation village and airfield
Investment
  • Mine and offsite infrastructure: $5.9 billion
  • Railway line: $1.2 billion
Jobs Mine:
  • Up to 1150 (construction)
  • Up to 2820 (operational)
Railway line:
  • Up to 1350 (construction)
  • Up to 120 (operational)

Environmental impact statement (EIS) process

Date Activity
Currently Supplementary information to EIS being prepared by proponent.
15 December 2012 to
11 February 2013
Public consultation on EIS
24 May 2011 Terms of reference for EIS (PDF icon 548 KB) released.
12 February 2011 to
28 March 2011
Draft terms of reference for EIS public consultation.
6 January 2011 Project deemed a 'controlled action' by federal environment minister. More information
26 November 2010 Gazettal of 'coordinated project' declaration.
18 November 2010 Project referred to federal environment minister.
22 October 2010 Application, including initial advice statement (PDF icon 1.79 MB), submitted.

Read more about the EIS process.

* Project information supplied by proponent and subject to change.