Carmichael Coal Mine and Rail Project
- Details
Project overview*
| EIS status | EIS active |
| Description | Open-cut and underground coal mine with a yield of 60 million tonnes per annum (from 2022); and railway line. |
| Proponent | Adani Mining Pty Ltd, a wholly owned subsidiary of India's Adani Group. |
| Location/s |
|
| Local government/s |
|
| Key features |
|
| Investment |
|
| Jobs | Mine:
|
Environmental impact statement (EIS) process
| Date | Activity |
|---|---|
| Currently | Supplementary information to EIS being prepared by proponent. |
| 15 December 2012 to 11 February 2013 |
Public consultation on EIS
|
| 24 May 2011 | Terms of reference for EIS ( |
| 12 February 2011 to 28 March 2011 |
Draft terms of reference for EIS public consultation. |
| 6 January 2011 | Project deemed a 'controlled action' by federal environment minister.
|
| 26 November 2010 | Gazettal of 'coordinated project' declaration. |
| 18 November 2010 | Project referred to federal environment minister. |
| 22 October 2010 | Application, including initial advice statement ( |
Read more about the EIS process.
* Project information supplied by proponent and subject to change.
Media releases
- Coordinator-General makes 100th decision (13 December 2012)