Skip links and keyboard navigation

New Acland Coal Mine Stage 3 Project

Project overview*

EIS status EIS active
Description Expansion of the existing New Acland open-cut coal mine, from 4.8 million tonnes per annum (Mtpa) to up to 7.5 Mtpa.
Proponent New Acland Coal Pty Ltd, a subsidiary of New Hope Corporation Limited
Location/s 35 km north-west of Toowoomba. Map
Local government/s Toowoomba Regional Council
Investment $896 million
Key features
  • development of parts of the Manning Vale and Willeroo resource areas
  • upgrades to existing coal handling and preparation plant and supporting infrastructure
  • new coal load-out facility and an approximately eight-kilometre rail spur
  • roadworks, water management structures, and relocation and potential upgrade of power supply.
Jobs
  • 260 (construction peak)
  • 435 (operational peak)

Project revised

The original terms of reference (TOR) for the project's EIS were finalised in October 2007 and New Acland Coal submitted the original EIS to the Coordinator-General in November 2009.

However, in response to concerns raised in March 2012 by the incoming Queensland Government about the project's potential impacts, the proponent revised the project, including reducing its scope.

New Acland Coal also proposed to move the existing Jondaryan rail coal load-out facility onto the mine site. An eight-kilometre rail spur would connect the facility to the existing rail line.

Due to the revisions, the Coordinator-General's environmental impact assessment of the project recommenced. New TOR for an EIS were finalised in March 2013, following public consultation.

On 9 November 2012 the then Commonwealth Department of Sustainability, Environment, Water, Population and Communities confirmed it had accepted the revised project proposal.

Environmental impact statement (EIS) process

Date Activity
Currently EIS and submissions being assessed.
18 January 2014 to
3 March 2014
New draft EIS public consultation
22 March 2013 New terms of reference for EIS (PDF icon 447 KB) released
1 December 2012 to
4 February 2013
New draft terms of reference for EIS public consultation.
14 November 2012 Confirmation by state government that, due to revisions to the project, including reductions to its scope, the EIS process would restart at the draft terms of reference for EIS stage.

Read the revised project overview (PDF icon 2.14 MB)
9 November 2012 Revisions to project proposal accepted by Commonwealth Minister for the Environment.
14 November 2009 to
3 February 2010
Original EIS public consultation
24 October 2007 Original terms of reference for EIS (PDF icon 575 KB) released.
21 July 2007 to
20 August 2007
Original draft terms of reference for EIS public consultation.
24 May 2007 Project deemed a 'controlled action' by Commonwealth Minister for the Environment. More information
18 May 2007 Gazettal of 'coordinated project' declaration.
24 April 2007 Application, including initial advice statement (PDF icon 483 KB), submitted.
23 April 2007 Project referred to Commonwealth Minister for the Environment.

Read more about the EIS process.

Separate EIS for water pipeline

The construction of a water pipeline from the Wetalla Wastewater Reclamation Facility in Toowoomba to the mine (one component of the proposed project) was expedited by the proponent, in accordance with section 32(1)(b) of the State Development and Public Works Organisation Act 1971.

This section of the Act allows proponents to prepare a separate environmental impact statement (EIS) that addresses the terms of reference relating to a particular component of a project.

The Coordinator-General recommended construction of the Wetalla Water Pipeline proceed, subject to conditions and recommendations.

The remainder of New Acland Coal Mine Stage 3 is still being assessed.

Media releases

* Project information supplied by proponent and subject to change.

Last updated on Tuesday, 11 March 2014